Renewable sites › Frodsham Marsh
Frodsham Marsh
Frodsham Marsh is operational in Cheshire West and Chester with a recorded capacity of 50.4 MW, and has been generating since 2016-11-15.
Planning and build timeline
| Application submitted | 2010-02-25 |
| Permission granted | 2012-10-19 32 months after submission |
| Operational | 2016-11-15 49 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — Cheshire West and Chester
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Runcorn EfW EfW Incineration · Operational | 100 | 3 km |
Ince Bio Power Advanced Conversion Technologies · Operational | 21.5 | 3.9 km |
Plot 8 Protos/Ince Marshes EfW Incineration · Under Construction | 35 | 4.3 km |
Leiria Way Car Park Battery · Operational | — | 5.2 km |
Granox Biogas Plant Anaerobic Digestion · Operational | 5 | 6 km |
Widnes 3MG Biomass/Mersey Bioenergy (CHP) Plant Biomass (dedicated) · Operational | 20 | 6.1 km |
Gowy Landfill Site, Cheshire (Extension) Landfill Gas · Operational | 6 | 8.2 km |
Gowy Landfill Site Landfill Gas · Operational | 1.6 | 8.2 km |
How big is Frodsham Marsh?
Frodsham Marsh has a recorded installed capacity of 50.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Frodsham Marsh?
REPD records the operator as Foresight/Belltown. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Frodsham Marsh approved and built?
The application was submitted on 2010-02-25. Permission was granted on 2012-10-19, 32 months later. The site became operational on 2016-11-15, 49 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3694.