PG2 Bolam Power Generator (Extension)

PG2 Bolam Power Generator (Extension) is operational in County Durham with a recorded capacity of 1.1 MW, and has been generating since 2004-06-01.

1.1 MW
Capacity
as recorded in REPD
Operational
Status
since 2004-06-01
Landfill Gas
Technology
CLP and Briagas
County Durham
Authority
England

Planning and build timeline

Application submitted2003-08-07
Permission granted2003-12-18
4 months after submission
Operational2004-06-01
5 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
PG2 Bolam Power Generation
Landfill Gas · Operational
10 km
Field at School Aycliffe Lane
Solar Photovoltaics · Operational
57.1 km
Preston Road AD Plant (Waste AD)
Anaerobic Digestion · Operational
2.88.1 km
Aldi Distribution Centre - Darlington
Solar Photovoltaics · Operational
1.210.5 km
Burtree Lane - Solar farm
Solar Photovoltaics · Under Construction
49.910.8 km
Rise Carr, Darlington / CLNR EES3-1
Battery · Operational
2.511.4 km
Chilton Energy Plant
Biomass (dedicated) · Operational
1811.6 km
Moor House Wind Farm
Wind Onshore · Operational
1213.8 km

How big is PG2 Bolam Power Generator (Extension)?

PG2 Bolam Power Generator (Extension) has a recorded installed capacity of 1.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates PG2 Bolam Power Generator (Extension)?

REPD records the operator as CLP and Briagas. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was PG2 Bolam Power Generator (Extension) approved and built?

The application was submitted on 2003-08-07. Permission was granted on 2003-12-18, 4 months later. The site became operational on 2004-06-01, 5 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 670.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council