Novarly ParcelRenewable sites

Renewable sitesMoor House Wind Farm

Moor House Wind Farm

Moor House Wind Farm is operational in Darlington with a recorded capacity of 12 MW, and has been generating since 2017-12-15.

12 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-12-15
Wind Onshore
Technology
Banks Renewables
Darlington
Authority
England

Planning and build timeline

Application submitted2011-03-14
Permission granted2011-10-19
7 months after submission
Operational2017-12-15
74 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Rise Carr, Darlington / CLNR EES3-1
Battery · Operational
2.55.1 km
Aldi Distribution Centre - Darlington
Solar Photovoltaics · Operational
1.25.8 km
Burtree Lane - Solar farm
Solar Photovoltaics · Under Construction
49.96.1 km
Preston Road AD Plant (Waste AD)
Anaerobic Digestion · Operational
2.86.4 km
Field at School Aycliffe Lane
Solar Photovoltaics · Operational
57.4 km
Land West Of Hunger Hill Farm
Solar Photovoltaics · Operational
57.6 km
High Meadow Farm
Solar Photovoltaics · Operational
48 km
Cowley Complex, Stockton on Tees
Solar Photovoltaics · Under Construction
1208 km

How big is Moor House Wind Farm?

Moor House Wind Farm has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Moor House Wind Farm?

REPD records the operator as Banks Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Moor House Wind Farm approved and built?

The application was submitted on 2011-03-14. Permission was granted on 2011-10-19, 7 months later. The site became operational on 2017-12-15, 74 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4642.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council