Aldi Distribution Centre - Darlington
Aldi Distribution Centre - Darlington is operational in Darlington with a recorded capacity of 1.2 MW, and has been generating since 2014-03-26.
Planning and build timeline
| Application submitted | 2013-07-11 |
| Permission granted | 2013-09-17 2 months after submission |
| Operational | 2014-03-26 6 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Nutrient-neutrality catchment — Teesmouth and Cleveland Coast SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Darlington’s record on solar
Darlington has decided 17 solar farms and approved 100%, taking a median of 1.8 months. See every solar farm decision in Darlington →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Burtree Lane - Solar farm Solar Photovoltaics · Under Construction | 49.9 | 0.6 km |
Rise Carr, Darlington / CLNR EES3-1 Battery · Operational | 2.5 | 1 km |
Moor House Wind Farm Wind Onshore · Operational | 12 | 5.8 km |
Preston Road AD Plant (Waste AD) Anaerobic Digestion · Operational | 2.8 | 6.4 km |
Field at School Aycliffe Lane Solar Photovoltaics · Operational | 5 | 6.8 km |
Land West Of Hunger Hill Farm Solar Photovoltaics · Operational | 5 | 7.4 km |
PG2 Bolam Power Generation Landfill Gas · Operational | 1 | 10.5 km |
PG2 Bolam Power Generator (Extension) Landfill Gas · Operational | 1.1 | 10.5 km |
How big is Aldi Distribution Centre - Darlington?
Aldi Distribution Centre - Darlington has a recorded installed capacity of 1.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Aldi Distribution Centre - Darlington?
REPD records the operator as Aldi. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Aldi Distribution Centre - Darlington approved and built?
The application was submitted on 2013-07-11. Permission was granted on 2013-09-17, 2 months later. The site became operational on 2014-03-26, 6 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1278.