Renewable sitesBurtree Lane - Solar farm

Burtree Lane - Solar farm

Burtree Lane - Solar farm is under construction in Darlington with a recorded capacity of 49.9 MW.

49.9 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Darlington Borough Council / Aura Power Solar
Darlington
Authority
England

Planning and build timeline

Application submitted2022-03-23
Permission granted2023-01-11
10 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Darlington’s record on solar

Darlington has decided 17 solar farms and approved 100%, taking a median of 1.8 months. See every solar farm decision in Darlington

Other built sites within 15 km

SiteMWDistance
Aldi Distribution Centre - Darlington
Solar Photovoltaics · Operational
1.20.6 km
Rise Carr, Darlington / CLNR EES3-1
Battery · Operational
2.51.1 km
Moor House Wind Farm
Wind Onshore · Operational
126.1 km
Preston Road AD Plant (Waste AD)
Anaerobic Digestion · Operational
2.87 km
Land West Of Hunger Hill Farm
Solar Photovoltaics · Operational
57.1 km
Field at School Aycliffe Lane
Solar Photovoltaics · Operational
57.3 km
PG2 Bolam Power Generator (Extension)
Landfill Gas · Operational
1.110.8 km
PG2 Bolam Power Generation
Landfill Gas · Operational
110.8 km

How big is Burtree Lane - Solar farm?

Burtree Lane - Solar farm has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Burtree Lane - Solar farm?

REPD records the operator as Darlington Borough Council / Aura Power Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Burtree Lane - Solar farm approved and built?

The application was submitted on 2022-03-23. Permission was granted on 2023-01-11, 10 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8529.