Novarly ParcelRenewable sites

Renewable sitesParsonage Barn (extension)

Parsonage Barn (extension)

Parsonage Barn (extension) is operational in Somerset with a recorded capacity of 7.6 MW, and has been generating since 2013-06-28.

7.6 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-06-28
Solar Photovoltaics
Technology
Private Developer
Somerset
Authority
England

Planning and build timeline

Application submitted2012-07-27
Permission granted2012-10-18
3 months after submission
Operational2013-06-28
8 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Somerset’s record on solar

Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset

Other built sites within 15 km

SiteMWDistance
Hurcott Copse Solar Farm
Solar Photovoltaics · Operational
102.6 km
Chard Solar Park
Solar Photovoltaics · Operational
36.2 km
Goldenhaye Field Solar Farm
Solar Photovoltaics · Operational
26.9 km
Lower Coombe Farm (Bean Field)
Solar Photovoltaics · Operational
17.4 km
Lower Coombe Farm Solar
Solar Photovoltaics · Operational
17.5 km
Wambrook Farm
Solar Photovoltaics · Operational
4.19.1 km
Lower Severalls Farm
Solar Photovoltaics · Operational
10.89.7 km
Helland Meads
Solar Photovoltaics · Operational
1.29.9 km

How big is Parsonage Barn (extension)?

Parsonage Barn (extension) has a recorded installed capacity of 7.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Parsonage Barn (extension)?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Parsonage Barn (extension) approved and built?

The application was submitted on 2012-07-27. Permission was granted on 2012-10-18, 3 months later. The site became operational on 2013-06-28, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1606.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council