Renewable sites › Lower Severalls Farm
Lower Severalls Farm
Lower Severalls Farm is operational in Somerset with a recorded capacity of 10.8 MW, and has been generating since 2017-10-18.
Planning and build timeline
| Application submitted | 2014-07-15 |
| Permission granted | 2014-09-19 2 months after submission |
| Operational | 2017-10-18 37 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
- Nutrient-neutrality catchment — Parrett Catchment
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Somerset’s record on solar
Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Lower Coombe Farm Solar Solar Photovoltaics · Operational | 1 | 4.1 km |
Pattemores Transport (Crewkern) Solar Photovoltaics · Under Construction | 2.1 | 4.3 km |
Lower Coombe Farm (Bean Field) Solar Photovoltaics · Operational | 1 | 4.6 km |
Hurcott Copse Solar Farm Solar Photovoltaics · Operational | 10 | 7.6 km |
Goldenhaye Field Solar Farm Solar Photovoltaics · Operational | 2 | 9.5 km |
Parsonage Barn (extension) Solar Photovoltaics · Operational | 7.6 | 9.7 km |
Westland Leisure Complex Solar Photovoltaics · Operational | 0.22 | 10.2 km |
Tesco Queensway Place Solar Photovoltaics · Operational | 0.3 | 11 km |
How big is Lower Severalls Farm?
Lower Severalls Farm has a recorded installed capacity of 10.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Lower Severalls Farm?
REPD records the operator as Sigma Solar Limited / OPDE. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Lower Severalls Farm approved and built?
The application was submitted on 2014-07-15. Permission was granted on 2014-09-19, 2 months later. The site became operational on 2017-10-18, 37 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2154.