Renewable sites › Hurcott Copse Solar Farm
Hurcott Copse Solar Farm
Hurcott Copse Solar Farm is operational in Somerset with a recorded capacity of 10 MW, and has been generating since 2015-03-20.
Planning and build timeline
| Application submitted | 2014-07-10 |
| Permission granted | 2014-09-19 2 months after submission |
| Operational | 2015-03-20 6 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
- Nutrient-neutrality catchment — Parrett Catchment
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Somerset’s record on solar
Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Parsonage Barn (extension) Solar Photovoltaics · Operational | 7.6 | 2.6 km |
Lower Coombe Farm Solar Solar Photovoltaics · Operational | 1 | 6.3 km |
Lower Coombe Farm (Bean Field) Solar Photovoltaics · Operational | 1 | 6.3 km |
Lower Severalls Farm Solar Photovoltaics · Operational | 10.8 | 7.6 km |
Goldenhaye Field Solar Farm Solar Photovoltaics · Operational | 2 | 7.6 km |
Chard Solar Park Solar Photovoltaics · Operational | 3 | 7.9 km |
Helland Meads Solar Photovoltaics · Operational | 1.2 | 11 km |
Wambrook Farm Solar Photovoltaics · Operational | 4.1 | 11 km |
How big is Hurcott Copse Solar Farm?
Hurcott Copse Solar Farm has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hurcott Copse Solar Farm?
REPD records the operator as Dillington Farms Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hurcott Copse Solar Farm approved and built?
The application was submitted on 2014-07-10. Permission was granted on 2014-09-19, 2 months later. The site became operational on 2015-03-20, 6 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2118.
Novarly Parcel · official public data, read properly · parcel.novarly.com