Chard Solar Park is operational in Somerset with a recorded capacity of 3 MW, and has been generating since 2016-03-23.

3 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-23
Solar Photovoltaics
Technology
Conergy
Somerset
Authority
England

Planning and build timeline

Application submitted2015-07-15
Permission granted2015-10-28
3 months after submission
Operational2016-03-23
5 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Somerset’s record on solar

Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset

Other built sites within 15 km

SiteMWDistance
Goldenhaye Field Solar Farm
Solar Photovoltaics · Operational
23 km
Wambrook Farm
Solar Photovoltaics · Operational
4.13.4 km
JB Wheaton
Battery · Operational
8.85 km
Marshwood Farm
Solar Photovoltaics · Operational
1.85.2 km
Parsonage Barn (extension)
Solar Photovoltaics · Operational
7.66.2 km
Lower Coombe Farm (Bean Field)
Solar Photovoltaics · Operational
17.4 km
Hurcott Copse Solar Farm
Solar Photovoltaics · Operational
107.9 km
Lower Coombe Farm Solar
Solar Photovoltaics · Operational
17.9 km

How big is Chard Solar Park?

Chard Solar Park has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Chard Solar Park?

REPD records the operator as Conergy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Chard Solar Park approved and built?

The application was submitted on 2015-07-15. Permission was granted on 2015-10-28, 3 months later. The site became operational on 2016-03-23, 5 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5102.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council