Otterham Down Wind Farm is operational in Cornwall with a recorded capacity of 3.2 MW, and has been generating since 2011-08-17.

3.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2011-08-17
Wind Onshore
Technology
Otter Power
Cornwall
Authority
England

Planning and build timeline

Application submitted2006-06-20
Permission granted2009-10-13
40 months after submission
Operational2011-08-17
22 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on onshore wind

Cornwall has decided 35 onshore wind schemes and approved 74%, taking a median of 7.5 months. See every onshore wind scheme decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Lower Tregeen, Davidstow - Wind Turbine
Wind Onshore · Under Construction
0.92.5 km
Saputo Dairy UK
Battery · Operational
4.7 km
Saputo Dairy UK
Solar Photovoltaics · Operational
4.24.7 km
Cold Northcott
Wind Onshore · Operational
6.66.3 km
Delabole (Repowering)
Wind Onshore · Operational
9.28.5 km
Canworthy Water
Solar Photovoltaics · Operational
418.7 km
Winsdon Farm
Solar Photovoltaics · Operational
511.5 km
Creathorne Farm - Solar Farm
Solar Photovoltaics · Operational
1.813.2 km

How big is Otterham Down Wind Farm?

Otterham Down Wind Farm has a recorded installed capacity of 3.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Otterham Down Wind Farm?

REPD records the operator as Otter Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Otterham Down Wind Farm approved and built?

The application was submitted on 2006-06-20. Permission was granted on 2009-10-13, 40 months later. The site became operational on 2011-08-17, 22 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3941.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council