Lower Tregeen, Davidstow - Wind Turbine is under construction in Cornwall with a recorded capacity of 0.9 MW.

0.9 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Wind Onshore
Technology
Powerquinn Limited
Cornwall
Authority
England

Planning and build timeline

Application submitted2018-11-20
Permission granted2019-03-05
3 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on onshore wind

Cornwall has decided 35 onshore wind schemes and approved 74%, taking a median of 7.5 months. See every onshore wind scheme decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Otterham Down Wind Farm
Wind Onshore · Operational
3.22.5 km
Saputo Dairy UK
Battery · Operational
3.1 km
Saputo Dairy UK
Solar Photovoltaics · Operational
4.23.1 km
Cold Northcott
Wind Onshore · Operational
6.64.4 km
Delabole (Repowering)
Wind Onshore · Operational
9.27.8 km
Canworthy Water
Solar Photovoltaics · Operational
419.1 km
Winsdon Farm
Solar Photovoltaics · Operational
511.5 km
Grange Farm (Cornwall)
Solar Photovoltaics · Operational
513.8 km

How big is Lower Tregeen, Davidstow - Wind Turbine?

Lower Tregeen, Davidstow - Wind Turbine has a recorded installed capacity of 0.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lower Tregeen, Davidstow - Wind Turbine?

REPD records the operator as Powerquinn Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lower Tregeen, Davidstow - Wind Turbine approved and built?

The application was submitted on 2018-11-20. Permission was granted on 2019-03-05, 3 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6818.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council