Lower Tregeen, Davidstow - Wind Turbine is under construction in Cornwall with a recorded capacity of 0.9 MW.
Planning and build timeline
| Application submitted | 2018-11-20 |
| Permission granted | 2019-03-05 3 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cornwall’s record on onshore wind
Cornwall has decided 35 onshore wind schemes and approved 74%, taking a median of 7.5 months. See every onshore wind scheme decision in Cornwall →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Otterham Down Wind Farm Wind Onshore · Operational | 3.2 | 2.5 km |
Saputo Dairy UK Battery · Operational | — | 3.1 km |
Saputo Dairy UK Solar Photovoltaics · Operational | 4.2 | 3.1 km |
Cold Northcott Wind Onshore · Operational | 6.6 | 4.4 km |
Delabole (Repowering) Wind Onshore · Operational | 9.2 | 7.8 km |
Canworthy Water Solar Photovoltaics · Operational | 41 | 9.1 km |
Winsdon Farm Solar Photovoltaics · Operational | 5 | 11.5 km |
Grange Farm (Cornwall) Solar Photovoltaics · Operational | 5 | 13.8 km |
How big is Lower Tregeen, Davidstow - Wind Turbine?
Lower Tregeen, Davidstow - Wind Turbine has a recorded installed capacity of 0.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Lower Tregeen, Davidstow - Wind Turbine?
REPD records the operator as Powerquinn Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Lower Tregeen, Davidstow - Wind Turbine approved and built?
The application was submitted on 2018-11-20. Permission was granted on 2019-03-05, 3 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6818.