Delabole (Repowering) is an operational 9.2 MW onshore wind farm in Cornwall, generating since 1 February 2011. Planning permission was granted on 12 December 2009, 20 months after submission. Operator of record: Good Energy Generation.

9.2 MW
Capacity
as recorded in REPD
Operational
Status
since 1 February 2011
Wind Onshore
Technology
Good Energy Generation
Cornwall
Authority
England

Planning and build timeline

Application submitted6 April 2008
Permission granted12 December 2009
20 months after submission
Operational1 February 2011
14 months after consent

Screening a site of your own?

RedlineUK · £39

Cornwall approves 74% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Delabole (Repowering)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on onshore wind

Cornwall has decided 35 onshore wind schemes and approved 74%, taking a median of 7.5 months. See every onshore wind scheme decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Battery · Operational
4.9 km
Solar Photovoltaics · Operational
4.24.9 km
Wind Onshore · Under Construction
0.97.8 km
Wind Onshore · Operational
3.28.5 km
Solar Photovoltaics · Operational
48.9 km
Wind Onshore · Operational
6.611.2 km
Solar Photovoltaics · Operational
212.2 km
Solar Photovoltaics · Operational
6.512.8 km

How big is Delabole (Repowering)?

Delabole (Repowering) has a recorded installed capacity of 9.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Delabole (Repowering)?

REPD records the operator as Good Energy Generation. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Delabole (Repowering) approved and built?

The application was submitted on 6 April 2008. Permission was granted on 12 December 2009, 20 months later. The site became operational on 1 February 2011, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3019.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode