Ockendon Landfill Solar Farm
Ockendon Landfill Solar Farm is operational in Thurrock with a recorded capacity of 38 MW, and has been generating since 2023-09-01.
Planning and build timeline
| Application submitted | 2014-07-29 |
| Permission granted | 2016-01-22 18 months after submission |
| Operational | 2023-09-01 91 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — Thurrock
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Thurrock’s record on solar
Thurrock has decided 17 solar farms and approved 94%, taking a median of 2.4 months. See every solar farm decision in Thurrock →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Ockendon Area III Landfill Gas · Operational | 8.5 | 0.2 km |
Ockendon 'B' Landfill Scheme Landfill Gas · Operational | 4.5 | 1.4 km |
Fen Lane, Bulphan Solar Farm Solar Photovoltaics · Under Construction | 49.9 | 1.7 km |
Bulphan Fen Solar Farm & Battery Storage Solar Photovoltaics · Under Construction | 49.9 | 2 km |
Bulphan Fen Solar Farm & Battery Storage Battery · Under Construction | — | 2 km |
Medebridge Road - Solar Farm Solar Photovoltaics · Operational | 49.9 | 2.6 km |
Little Belhus Restoration Site Wind Onshore · Operational | 1 | 2.9 km |
Clay Tye Farm Phase 1 - Storage Facility Battery · Operational | 49.5 | 3.3 km |
How big is Ockendon Landfill Solar Farm?
Ockendon Landfill Solar Farm has a recorded installed capacity of 38 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ockendon Landfill Solar Farm?
REPD records the operator as NTR Plc. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ockendon Landfill Solar Farm approved and built?
The application was submitted on 2014-07-29. Permission was granted on 2016-01-22, 18 months later. The site became operational on 2023-09-01, 91 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2053.