Renewable sitesClay Tye Farm Phase 1 - Storage Facility

Clay Tye Farm Phase 1 - Storage Facility

Clay Tye Farm Phase 1 - Storage Facility is operational in Havering with a recorded capacity of 49.5 MW, and has been generating since 2024-03-22.

49.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2024-03-22
Battery
Technology
Harmony Energy Storage
Havering
Authority
England

Planning and build timeline

Application submitted2017-04-28
Permission granted2023-03-06
70 months after submission
Operational2024-03-22
13 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Clay Tye Farm Phase 2 - Storage Facility
Battery · Operational
49.50 km
Cranham Golf Course Solar Park
Solar Photovoltaics · Operational
2.61.1 km
Fen Lane, Bulphan Solar Farm
Solar Photovoltaics · Under Construction
49.92.3 km
Ockendon Landfill Solar Farm
Solar Photovoltaics · Operational
383.3 km
Ockendon Area III
Landfill Gas · Operational
8.53.4 km
Bulphan Fen Solar Farm & Battery Storage
Solar Photovoltaics · Under Construction
49.93.5 km
Bulphan Fen Solar Farm & Battery Storage
Battery · Under Construction
3.5 km
Little Belhus Restoration Site
Wind Onshore · Operational
13.5 km

How big is Clay Tye Farm Phase 1 - Storage Facility?

Clay Tye Farm Phase 1 - Storage Facility has a recorded installed capacity of 49.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Clay Tye Farm Phase 1 - Storage Facility?

REPD records the operator as Harmony Energy Storage. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Clay Tye Farm Phase 1 - Storage Facility approved and built?

The application was submitted on 2017-04-28. Permission was granted on 2023-03-06, 70 months later. The site became operational on 2024-03-22, 13 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11720.