Novarly ParcelRenewable planning

Renewable planning SolarThurrock

Solar planning in Thurrock

Thurrock has decided 17 solar farms and approved 94% of them, taking a median of 2.4 months to decide. Consented capacity: 181 MW. 2 applications still awaiting a decision.

94%
Approved
16 granted · 1 refused
2.4 mo
Median decision
UK 2.3 mo
181 MW
Consented
23 MW refused
0
Appeals
no appeals recorded

How Thurrock compares

Against the 298 UK authorities with 5+ solar decisions, Thurrock sits in the 38th percentile for approval rate (1 points above the England average) and the 48th percentile for speed.

Decisions by year

35Approved — 1 (2013)113Approved — 1 (2015)115Approved — 1 (2016)Refused — 1 (2016)216Approved — 1 (2019)119Approved — 1 (2021)121Approved — 2 (2022)222Approved — 1 (2023)123Approved — 3 (2024)324Approved — 3 (2025)325Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (21)

SchemeMWStatusDecided
Tesco, Cygnet View - Solar PV Arrays
Tesco Plc · 25/01468/PASOND · 2 mo to decide
1.05Awaiting Construction2026-03-09
Ocado Operating Limited, New Purfleet Road - Solar Panels
Saber Renewable Energy Limited · 25/00243/PASOL · 1.8 mo to decide
2.8Awaiting Construction2025-05-06
Harris Academy Chafford Hundred, Chafford Hundred - Solar Aarray
Ameresco · 25/00159/PASOL · 1.1 mo to decide
0.22Awaiting Construction2025-03-18
Tilbury Green Power Station - Solar PV Panels
Equitix Limited · 24/01321/PASOL · 1.8 mo to decide
0.3Awaiting Construction2025-02-17
DSV Road, Stonehouse Lane - Solar Panels
DSV Road · 24/00963/PASOL · 2 mo to decide
0.26Awaiting Construction2024-11-12
Intu Lakeside, West Thurrock Way - Solar Panels
Global Mutual · 24/00777/PASOL · 1.8 mo to decide
1.31Awaiting Construction2024-09-12
Aveley Landfill, Sandy Lane - PV Solar Array & Battery Energy Storage
Infinis Energy Services Limited · 24/00141/FUL · 5.6 mo to decide
16Awaiting Construction2024-07-24
Marsh Farm, Fobbing - Solar Arrays & Battery Storage
Rayleigh Green Limited · 23/00847/FUL
49.9Application Withdrawn2024-05-09
Marsh Farm
Rayleigh Green · 21/01635/FUL · 20.3 mo to decide
49.9Revised2023-06-12
Ford Retail, Triton Centre Weston Avenue - Solar Panels
Fidelity UK Real Estate Fund · 22/01509/PASOND · 1.8 mo to decide
0.79Awaiting Construction2023-01-03
Medebridge Road - Solar Farm
Medebridge Solar · 21/02159/FUL · 2.8 mo to decide
49.9Operational2022-05-10
Morrisons - Solar Photovoltaic Panels
WM Morrisons Supermarkets Plc · 22/00261/PASOND · 1.8 mo to decide
0.43Awaiting Construction2022-04-13
Bulphan Fen Solar Farm & Battery Storage
Warley Green Limited · 21/00077/FUL · 9.1 mo to decide
49.9Under Construction2021-10-21
Tesco Store Cygnet View
Tesco Stores · 19/00333/PASOND · 1.8 mo to decide
0.6Awaiting Construction2019-04-29
Tilbury LCY2
Amazon UK Services/ Push Energy · 18/01114/FUL
4Operational2018-08-07
The Place Solar Farm
Be Renewables · 14/01278/FUL · 23.6 mo to decide
23.2Application Refused2016-11-25
Land adjacent to the former Coryton Refinery
S4N Worsted/Gamma Energy Exeter · 15/00877/FUL · 4.7 mo to decide
5Abandoned2016-02-12
Ockendon Landfill Solar Farm
NTR Plc · 14/00836/FUL · 17.8 mo to decide
38Operational2016-01-22
Barvills Solar Farm
BE Renewables/Barvills Solar Limited · 15/00288/FUL · 4.6 mo to decide
5Operational2015-08-07
Barvills Solar Farm
Barvills Solar Limited (BE Renewables) · 14/01124/FUL
11.6Revised2015-03-16
Fairwind Farm
MS Power Projects Ltd · 13/00543/FUL · 5.5 mo to decide
10Operational2013-11-25

Does Thurrock approve solar farms?

Yes — of the 17 solar farms Thurrock has decided, 94% were approved (16 granted, 1 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Thurrock?

The median time from application to decision is 2.4 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Thurrock consented?

181 MW has been consented across 16 approved schemes, with 23 MW refused. A further 2 applications awaits a decision.

Other technologies in Thurrock

Battery storage in ThurrockOnshore wind in Thurrock

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com