Renewable sites › North Kyle Energy Project
North Kyle Energy Project
North Kyle Energy Project is under construction in Scotland with a recorded capacity of 205.8 MW.
Planning and build timeline
| Application submitted | 2019-09-27 |
| Permission granted | 2021-06-30 21 months after submission |
| Operational | not recorded |
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
South Kyle Wind Farm Wind Onshore · Operational | 240 | 5.7 km |
Pencloe Wind Farm Wind Onshore · Under Construction | 81 | 7.3 km |
Enoch Hill Wind Onshore · Under Construction | 70 | 7.9 km |
Garlaff Landfill (Extension) Landfill Gas · Operational | 3 | 9.4 km |
Garlaff Landfill Landfill Gas · Operational | 1.3 | 9.4 km |
Dersalloch Wind Onshore · Operational | 69 | 9.7 km |
Benbrack Wind Farm Wind Onshore · Operational | 67.1 | 9.9 km |
Windy Standard III Wind Farm (Brockloch Rig Phase 2) Wind Onshore · Under Construction | 87.6 | 11.2 km |
How big is North Kyle Energy Project?
North Kyle Energy Project has a recorded installed capacity of 205.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates North Kyle Energy Project?
REPD records the operator as Brockwell Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was North Kyle Energy Project approved and built?
The application was submitted on 2019-09-27. Permission was granted on 2021-06-30, 21 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6607.