Renewable sites › Garlaff Landfill (Extension)
Garlaff Landfill (Extension)
Garlaff Landfill (Extension) is operational in East Ayrshire with a recorded capacity of 3 MW, and has been generating since 2003-12-29.
Planning and build timeline
| Application submitted | 2003-08-13 |
| Permission granted | 2003-12-18 4 months after submission |
| Operational | 2003-12-29 0 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Garlaff Landfill Landfill Gas · Operational | 1.3 | 0 km |
Coylton Substation, Coylton - Battery Energy Storage Battery · Under Construction | 50 | 6.9 km |
Pencloe Wind Farm Wind Onshore · Under Construction | 81 | 7.7 km |
Enoch Hill Wind Onshore · Under Construction | 70 | 9.3 km |
North Kyle Energy Project Wind Onshore · Under Construction | 205.8 | 9.4 km |
South Kyle Wind Farm Wind Onshore · Operational | 240 | 12.5 km |
Hare Hill Extension Wind Onshore · Operational | 29.8 | 13.5 km |
Hare Hill (East Ayrshire) Wind Onshore · Operational | 13.2 | 13.5 km |
How big is Garlaff Landfill (Extension)?
Garlaff Landfill (Extension) has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Garlaff Landfill (Extension)?
REPD records the operator as Garlaff Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Garlaff Landfill (Extension) approved and built?
The application was submitted on 2003-08-13. Permission was granted on 2003-12-18, 4 months later. The site became operational on 2003-12-29, 0 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 671.
Novarly Parcel · official public data, read properly · parcel.novarly.com