Novarly ParcelRenewable sites

Renewable sitesDersalloch

Dersalloch

Dersalloch is an operational 69 MW onshore wind farm in Scotland, generating since 15 August 2016. Planning permission was granted on 23 July 2014, 108 months after submission. Operator of record: Scottish Power Renewables.

69 MW
Capacity
as recorded in REPD
Operational
Status
since 15 August 2016
Wind Onshore
Technology
Scottish Power Renewables
National
Authority
Scotland

Planning and build timeline

Application submitted29 July 2005
Permission granted23 July 2014
108 months after submission
Operational15 August 2016
25 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Dersalloch’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Under Construction
205.89.7 km
Wind Onshore · Operational
67.111.9 km
Wind Onshore · Operational
24012.5 km
Solar Photovoltaics · Under Construction
4014.8 km
Battery · Under Construction
4514.8 km

How big is Dersalloch?

Dersalloch has a recorded installed capacity of 69 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dersalloch?

REPD records the operator as Scottish Power Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dersalloch approved and built?

The application was submitted on 29 July 2005. Permission was granted on 23 July 2014, 108 months later. The site became operational on 15 August 2016, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4269.