Benbrack Wind Farm is an operational 67.1 MW onshore wind farm in Scotland. Planning permission was granted on 15 September 2017, 34 months after submission. Operator of record: E.ON Renewables / Red Rock Power Limited.

67.1 MW
Capacity
as recorded in REPD
Operational
Status
no operational date
Wind Onshore
Technology
E.ON Renewables / Red Rock Power Limited
National
Authority
Scotland

Planning and build timeline

Application submitted20 November 2014
Permission granted15 September 2017
34 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Benbrack Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Under Construction
87.64.6 km
Wind Onshore · Operational
2405.7 km
Wind Onshore · Operational
907.5 km
Wind Onshore · Operational
438.5 km
Wind Onshore · Operational
21.68.8 km
Wind Onshore · Under Construction
205.89.9 km
Wind Onshore · Operational
5010 km
Wind Onshore · Under Construction
410.5 km

How big is Benbrack Wind Farm?

Benbrack Wind Farm has a recorded installed capacity of 67.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Benbrack Wind Farm?

REPD records the operator as E.ON Renewables / Red Rock Power Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Benbrack Wind Farm approved and built?

The application was submitted on 20 November 2014. Permission was granted on 15 September 2017, 34 months later. REPD does not record an operational date.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3503.