Windy Standard III Wind Farm (Brockloch Rig Phase 2)

Windy Standard III Wind Farm (Brockloch Rig Phase 2) is an 87.6 MW onshore wind farm under construction in Scotland. Planning permission was granted on 23 March 2021, 51 months after submission. Operator of record: Fred Olsen Renewables.

87.6 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Wind Onshore
Technology
Fred Olsen Renewables
National
Authority
Scotland

Planning and build timeline

Application submitted9 December 2016
Permission granted23 March 2021
51 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Windy Standard III Wind Farm (Brockloch Rig Phase 2)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
903 km
Wind Onshore · Operational
434 km
Wind Onshore · Operational
21.64.4 km
Wind Onshore · Operational
67.14.6 km
Wind Onshore · Operational
2405.6 km
Wind Onshore · Operational
505.8 km
Wind Onshore · Under Construction
708.9 km
Wind Onshore · Under Construction
8110.3 km

How big is Windy Standard III Wind Farm (Brockloch Rig Phase 2)?

Windy Standard III Wind Farm (Brockloch Rig Phase 2) has a recorded installed capacity of 87.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Windy Standard III Wind Farm (Brockloch Rig Phase 2)?

REPD records the operator as Fred Olsen Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Windy Standard III Wind Farm (Brockloch Rig Phase 2) approved and built?

The application was submitted on 9 December 2016. Permission was granted on 23 March 2021, 51 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4615.