Novarly ParcelRenewable sites

Renewable sitesNickle Farm

Nickle Farm

Nickle Farm is operational in Canterbury with a recorded capacity of 0.35 MW, and has been generating since 2021-08-01.

0.35 MW
Capacity
as recorded in REPD
Operational
Status
since 2021-08-01
Solar Photovoltaics
Technology
Beba Energy
Canterbury
Authority
England

Planning and build timeline

Application submitted2021-02-09
Permission granted2021-12-24
10 months after submission
Operational2021-08-01

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Canterbury’s record on solar

Canterbury has decided 20 solar farms and approved 95%, taking a median of 2.3 months. See every solar farm decision in Canterbury

Other built sites within 15 km

SiteMWDistance
Shelford Landfill Scheme
Landfill Gas · Operational
1.98.2 km
Shelford Generation Plant II
Landfill Gas · Operational
88.3 km
Abbey Fields Farm
Solar Photovoltaics · Operational
5.39.2 km
Littlebourne
Solar Photovoltaics · Operational
1710.3 km
Cleve Hill Solar Project
Solar Photovoltaics · Operational
37310.4 km
Cleve Hill Solar Project
Battery · Operational
15010.4 km
Woodlands Farm Solar Park
Solar Photovoltaics · Operational
1011.3 km
Molehill Farm
Solar Photovoltaics · Operational
1812.2 km

How big is Nickle Farm?

Nickle Farm has a recorded installed capacity of 0.35 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Nickle Farm?

REPD records the operator as Beba Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Nickle Farm approved and built?

The application was submitted on 2021-02-09. Permission was granted on 2021-12-24, 10 months later. The site became operational on 2021-08-01.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8448.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council