Nickle Farm

Nickle Farm is an operational 0.35 MW solar farm in Canterbury, generating since 1 August 2021. Planning permission was granted on 24 December 2021, 10 months after submission. Operator of record: Beba Energy.

0.35 MW
Capacity
as recorded in REPD
Operational
Status
since 1 August 2021
Solar Photovoltaics
Technology
Beba Energy
Canterbury
Authority
England

Planning and build timeline

Application submitted9 February 2021
Permission granted24 December 2021
10 months after submission
Operational1 August 2021

Screening a site of your own?

RedlineUK · £39

Canterbury approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Nickle Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Canterbury’s record on solar

Canterbury has decided 20 solar farms and approved 95%, taking a median of 2.3 months. See every solar farm decision in Canterbury

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
1.98.2 km
Landfill Gas · Operational
88.3 km
Solar Photovoltaics · Operational
5.39.2 km
Solar Photovoltaics · Operational
1710.3 km
Battery · Operational
15010.4 km
Solar Photovoltaics · Operational
37310.4 km
Solar Photovoltaics · Operational
1011.3 km
Solar Photovoltaics · Operational
1812.2 km

How big is Nickle Farm?

Nickle Farm has a recorded installed capacity of 0.35 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Nickle Farm?

REPD records the operator as Beba Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Nickle Farm approved and built?

The application was submitted on 9 February 2021. Permission was granted on 24 December 2021, 10 months later. The site became operational on 1 August 2021.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8448.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode