Littlebourne

Littlebourne is an operational 17 MW solar farm in Canterbury, generating since 13 November 2014. Planning permission was granted on 8 January 2014, 3 months after submission. Operator of record: Bluefield Solar Income Fund.

17 MW
Capacity
as recorded in REPD
Operational
Status
since 13 November 2014
Solar Photovoltaics
Technology
Bluefield Solar Income Fund
Canterbury
Authority
England

Planning and build timeline

Application submitted2 October 2013
Permission granted8 January 2014
3 months after submission
Operational13 November 2014
10 months after consent

Screening a site of your own?

RedlineUK · £39

Canterbury approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Littlebourne’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Canterbury’s record on solar

Canterbury has decided 20 solar farms and approved 95%, taking a median of 2.3 months. See every solar farm decision in Canterbury

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
1.94.1 km
Landfill Gas · Operational
84.2 km
Solar Photovoltaics · Operational
105.9 km
Solar Photovoltaics · Operational
16.1 km
Solar Photovoltaics · Operational
489.2 km
Solar Photovoltaics · Operational
11.59.5 km
Solar Photovoltaics · Operational
1810.1 km
Solar Photovoltaics · Operational
0.3510.3 km

How big is Littlebourne?

Littlebourne has a recorded installed capacity of 17 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Littlebourne?

REPD records the operator as Bluefield Solar Income Fund. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Littlebourne approved and built?

The application was submitted on 2 October 2013. Permission was granted on 8 January 2014, 3 months later. The site became operational on 13 November 2014, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2379.