Novarly ParcelRenewable sites

Renewable sitesMolehill Farm

Molehill Farm

Molehill Farm is operational in Canterbury with a recorded capacity of 18 MW, and has been generating since 2015-03-31.

18 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-03-31
Solar Photovoltaics
Technology
Bluefield Solar Income Fund
Canterbury
Authority
England

Planning and build timeline

Application submitted2013-10-30
Permission granted2014-02-05
3 months after submission
Operational2015-03-31
14 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Canterbury’s record on solar

Canterbury has decided 20 solar farms and approved 95%, taking a median of 2.3 months. See every solar farm decision in Canterbury

Other built sites within 15 km

SiteMWDistance
Owls Hatch Road
Solar Photovoltaics · Operational
481.1 km
Woodlands Farm Solar Park
Solar Photovoltaics · Operational
104.4 km
Shelford Generation Plant II
Landfill Gas · Operational
86.4 km
Shelford Landfill Scheme
Landfill Gas · Operational
1.96.6 km
Littlebourne
Solar Photovoltaics · Operational
1710.1 km
Kentish Flats 2
Wind Offshore · Operational
49.510.4 km
St Nicholas Court Farm (AD)
Anaerobic Digestion · Operational
1.211 km
Kentish Flats�
Wind Offshore · Operational
9011.6 km

How big is Molehill Farm?

Molehill Farm has a recorded installed capacity of 18 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Molehill Farm?

REPD records the operator as Bluefield Solar Income Fund. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Molehill Farm approved and built?

The application was submitted on 2013-10-30. Permission was granted on 2014-02-05, 3 months later. The site became operational on 2015-03-31, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2367.

Novarly Parcel · official public data, read properly · parcel.novarly.com