Renewable sitesShelford Landfill Scheme

Shelford Landfill Scheme

Shelford Landfill Scheme is an operational 1.9 MW landfill gas site in Canterbury, generating since 30 December 2001. Planning permission was granted on 27 October 1997, 15 months after submission. Operator of record: Brett Waste Management Ltd.

1.9 MW
Capacity
as recorded in REPD
Operational
Status
since 30 December 2001
Landfill Gas
Technology
Brett Waste Management Ltd
Canterbury
Authority
England

Planning and build timeline

Application submitted1 August 1996
Permission granted27 October 1997
15 months after submission
Operational30 December 2001
50 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Canterbury: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Shelford Landfill Scheme’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
80.2 km
Solar Photovoltaics · Operational
103.5 km
Solar Photovoltaics · Operational
174.1 km
Solar Photovoltaics · Operational
486 km
Solar Photovoltaics · Operational
186.6 km
Solar Photovoltaics · Operational
0.358.2 km
Solar Photovoltaics · Operational
19.8 km
Anaerobic Digestion · Operational
1.211.9 km

How big is Shelford Landfill Scheme?

Shelford Landfill Scheme has a recorded installed capacity of 1.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Shelford Landfill Scheme?

REPD records the operator as Brett Waste Management Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Shelford Landfill Scheme approved and built?

The application was submitted on 1 August 1996. Permission was granted on 27 October 1997, 15 months later. The site became operational on 30 December 2001, 50 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 578.