Novarly ParcelRenewable sites

Renewable sitesNewton Marsh Wind Project

Newton Marsh Wind Project

Newton Marsh Wind Project is an operational 4.6 MW onshore wind farm in East Lindsey, generating since 30 April 2014. Planning permission was granted on 28 May 2009, 16 months after submission. Operator of record: TCI Renewables.

4.6 MW
Capacity
as recorded in REPD
Operational
Status
since 30 April 2014
Wind Onshore
Technology
TCI Renewables
East Lindsey
Authority
England

Planning and build timeline

Application submitted29 January 2008
Permission granted28 May 2009
16 months after submission
Operational30 April 2014
59 months after consent

Screening a site of your own?

RedlineUK · £39

East Lindsey approves 50% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Newton Marsh Wind Project’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Lindsey’s record on onshore wind

East Lindsey has decided 14 onshore wind schemes and approved 50%, taking a median of 15.9 months. See every onshore wind scheme decision in East Lindsey

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
16.40.7 km
Solar Photovoltaics · Operational
0.54.9 km
Solar Photovoltaics · Under Construction
0.369 km
Solar Photovoltaics · Operational
209.8 km
Solar Photovoltaics · Operational
1.1210.3 km
Wind Onshore · Operational
1610.4 km
Solar Photovoltaics · Operational
110.4 km
Solar Photovoltaics · Operational
27.110.4 km

How big is Newton Marsh Wind Project?

Newton Marsh Wind Project has a recorded installed capacity of 4.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Newton Marsh Wind Project?

REPD records the operator as TCI Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Newton Marsh Wind Project approved and built?

The application was submitted on 29 January 2008. Permission was granted on 28 May 2009, 16 months later. The site became operational on 30 April 2014, 59 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3827.

Novarly Parcel · official public data, read properly · parcel.novarly.com