Novarly ParcelRenewable sites

Renewable sitesNew Barn Farm

New Barn Farm

New Barn Farm is an operational 4.5 MW onshore wind farm in Burnley, generating since 1 February 2007. Planning permission was granted on 23 February 2004, 18 months after submission. Operator of record: Private Developer.

4.5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 February 2007
Wind Onshore
Technology
Private Developer
Burnley
Authority
England

Planning and build timeline

Application submitted2 September 2002
Permission granted23 February 2004
18 months after submission
Operational1 February 2007
35 months after consent

Screening a site of your own?

RedlineUK · £39

Burnley approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with New Barn Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Burnley’s record on onshore wind

Burnley has decided 8 onshore wind schemes and approved 63%, taking a median of 9.4 months. See every onshore wind scheme decision in Burnley

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
7.50.3 km
Solar Photovoltaics · Operational
1.183.3 km
Landfill Gas · Operational
1.84.1 km
Landfill Gas · Operational
1.24.5 km
Landfill Gas · Operational
1.85.6 km
Landfill Gas · Operational
1.95.9 km
Landfill Gas · Operational
26 km
Landfill Gas · Operational
1.96.2 km

How big is New Barn Farm?

New Barn Farm has a recorded installed capacity of 4.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates New Barn Farm?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was New Barn Farm approved and built?

The application was submitted on 2 September 2002. Permission was granted on 23 February 2004, 18 months later. The site became operational on 1 February 2007, 35 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4685.

Novarly Parcel · official public data, read properly · parcel.novarly.com