Whinney Hill Waste Disposal Site

Whinney Hill Waste Disposal Site is operational in Hyndburn with a recorded capacity of 1.2 MW, and has been generating since 1999-01-08.

1.2 MW
Capacity
as recorded in REPD
Operational
Status
since 1999-01-08
Landfill Gas
Technology
Combined Landfill Projects (CLP)
Hyndburn
Authority
England

Planning and build timeline

Application submitted1997-12-02
Permission granted1998-03-04
3 months after submission
Operational1999-01-08
10 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Whinney Hill II Energy
Landfill Gas · Operational
1.80.4 km
Altham Business Park - Solar Panels
Solar Photovoltaics · Operational
1.183.1 km
Hameldon Hill extension
Wind Onshore · Operational
7.54.3 km
New Barn Farm
Wind Onshore · Operational
4.54.5 km
ENWL Training Academy
Solar Photovoltaics · Operational
0.35.5 km
Hyndburn Wind Farm
Wind Onshore · Operational
246.1 km
Total Food Services, North Road - Solar Panels
Solar Photovoltaics · Under Construction
0.228.2 km
Balle Street
Battery · Under Construction
9.8 km

How big is Whinney Hill Waste Disposal Site?

Whinney Hill Waste Disposal Site has a recorded installed capacity of 1.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Whinney Hill Waste Disposal Site?

REPD records the operator as Combined Landfill Projects (CLP). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Whinney Hill Waste Disposal Site approved and built?

The application was submitted on 1997-12-02. Permission was granted on 1998-03-04, 3 months later. The site became operational on 1999-01-08, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 730.