Whinney Hill Waste Disposal Site
Whinney Hill Waste Disposal Site is an operational 1.2 MW landfill gas site in Hyndburn, generating since 8 January 1999. Planning permission was granted on 4 March 1998, 3 months after submission. Operator of record: Combined Landfill Projects (CLP).
Planning and build timeline
| Application submitted | 2 December 1997 |
| Permission granted | 4 March 1998 3 months after submission |
| Operational | 8 January 1999 10 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Hyndburn: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Whinney Hill Waste Disposal Site’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
- Green Belt — Hyndburn
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Landfill Gas · Operational | 1.8 | 0.4 km |
Solar Photovoltaics · Operational | 1.18 | 3.1 km |
Wind Onshore · Operational | 7.5 | 4.3 km |
Wind Onshore · Operational | 4.5 | 4.5 km |
Solar Photovoltaics · Operational | 0.3 | 5.5 km |
Wind Onshore · Operational | 24 | 6.1 km |
Solar Photovoltaics · Under Construction | 0.22 | 8.2 km |
Battery · Under Construction | — | 9.8 km |
How big is Whinney Hill Waste Disposal Site?
Whinney Hill Waste Disposal Site has a recorded installed capacity of 1.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Whinney Hill Waste Disposal Site?
REPD records the operator as Combined Landfill Projects (CLP). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Whinney Hill Waste Disposal Site approved and built?
The application was submitted on 2 December 1997. Permission was granted on 4 March 1998, 3 months later. The site became operational on 8 January 1999, 10 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 730.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode