Hameldon Hill extension
Hameldon Hill extension is operational in Burnley with a recorded capacity of 7.5 MW, and has been generating since 2013-04-25.
Planning and build timeline
| Application submitted | 2009-12-30 |
| Permission granted | 2010-12-17 12 months after submission |
| Operational | 2013-04-25 28 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Burnley’s record on onshore wind
Burnley has decided 8 onshore wind schemes and approved 63%, taking a median of 9.4 months. See every onshore wind scheme decision in Burnley →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
New Barn Farm Wind Onshore · Operational | 4.5 | 0.3 km |
Altham Business Park - Solar Panels Solar Photovoltaics · Operational | 1.18 | 3.3 km |
Whinney Hill II Energy Landfill Gas · Operational | 1.8 | 3.9 km |
Whinney Hill Waste Disposal Site Landfill Gas · Operational | 1.2 | 4.3 km |
Queen's Park Road Energy Landfill Gas · Operational | 1.8 | 5.9 km |
Deerplay Landfill Site Landfill Gas · Operational | 2 | 6.1 km |
Rowley Landfill Gas · Operational | 1.9 | 6.2 km |
Queens Park Energy Landfill Gas · Operational | 1.9 | 6.5 km |
How big is Hameldon Hill extension?
Hameldon Hill extension has a recorded installed capacity of 7.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hameldon Hill extension?
REPD records the operator as RWE NPower Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hameldon Hill extension approved and built?
The application was submitted on 2009-12-30. Permission was granted on 2010-12-17, 12 months later. The site became operational on 2013-04-25, 28 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3761.