Queen's Park Road Energy is operational in Burnley with a recorded capacity of 1.8 MW, and has been generating since 2000-09-01.

1.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2000-09-01
Landfill Gas
Technology
Combined Landfill Projects (CLP)
Burnley
Authority
England

Planning and build timeline

Application submitted1992-03-26
Permission granted1992-08-20
5 months after submission
Operational2000-09-01
96 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Rowley
Landfill Gas · Operational
1.90.4 km
Queens Park Energy
Landfill Gas · Operational
1.90.6 km
Widow Hill, Balderstone Lane - Battery Energy Storage System
Battery · Under Construction
701.2 km
Deerplay Landfill Site
Landfill Gas · Operational
25.2 km
New Barn Farm
Wind Onshore · Operational
4.55.6 km
Hameldon Hill extension
Wind Onshore · Operational
7.55.9 km
Coal Clough Wind Farm Repowering
Wind Onshore · Operational
167.4 km
Coal Clough Wind Farm
Wind Onshore · Operational
9.67.4 km

How big is Queen's Park Road Energy?

Queen's Park Road Energy has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Queen's Park Road Energy?

REPD records the operator as Combined Landfill Projects (CLP). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Queen's Park Road Energy approved and built?

The application was submitted on 1992-03-26. Permission was granted on 1992-08-20, 5 months later. The site became operational on 2000-09-01, 96 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 731.