Onshore wind planning in Burnley

Burnley has decided 8 onshore wind schemes and approved 63% of them, taking a median of 9.4 months to decide. Consented capacity: 45 MW.

63%
Approved
5 granted · 3 refused
9.4 mo
Median decision
UK 11.5 mo
45 MW
Consented
15 MW refused
1
Appeals
1 allowed on appeal

How Burnley compares

Against the 75 UK authorities with 5+ onshore wind decisions, Burnley sits in the 36th percentile for approval rate (5 points below the England average) and the 78th percentile for speed.

Decisions by year

35Approved — 1 (2010)110Approved — 1 (2013)113Approved — 1 (2017)117
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (8)

SchemeMWStatusDecided
Hameldon Hill Wind Farm (extension 2)
FAB Energy · APP/2016/0263 · 13.5 mo to decide
7.1Planning Permission Expired2017-07-28
Coal Clough Wind Farm Repowering
Coal Clough Wind Farm · APP/2009/0758 · 37 mo to decide
16Operational2013-01-21
Hameldon Hill extension
RWE NPower Renewables · APP/2009/0756 · 11.6 mo to decide
7.5Operational2010-12-17
New Barn Farm
Private Developer · APP/2002/0516 · 17.7 mo to decide
4.5Operational2004-02-23
White Hill
E.ON UK · 12/02/656 · 3.2 mo to decide
12Application Refused2003-03-18
Black Scout Wind Farm
Renewable Energy Systems (RES) · 4 mo to decide
2Application Refused2000-05-25
Warcock Hill Project
Wind Turbine Developments Ltd · 4 mo to decide
1Application Refused2000-05-25
Coal Clough Wind Farm
Renewable Energy Systems (RES) · 91/0920 & APP/2005/0867 · 7.3 mo to decide
9.6Operational1992-07-03

Does Burnley approve onshore wind schemes?

Yes — of the 8 onshore wind schemes Burnley has decided, 63% were approved (5 granted, 3 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Burnley?

The median time from application to decision is 9.4 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Burnley consented?

45 MW has been consented across 5 approved schemes, with 15 MW refused. There are no applications currently awaiting a decision.

Other technologies in Burnley

Solar in BurnleyBattery storage in Burnley

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.