Novarly ParcelRenewable sites

Renewable sitesNetley Landfill Solar

Netley Landfill Solar

Netley Landfill Solar is an operational 12 MW solar farm in Eastleigh, generating since 31 March 2017. Planning permission was granted on 30 October 2014, 3 months after submission. Operator of record: REG Solarpower/Veolia.

12 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2017
Solar Photovoltaics
Technology
REG Solarpower/Veolia
Eastleigh
Authority
England

Planning and build timeline

Application submitted5 August 2014
Permission granted30 October 2014
3 months after submission
Operational31 March 2017
29 months after consent

Screening a site of your own?

RedlineUK · £39

Eastleigh approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Netley Landfill Solar’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Eastleigh’s record on solar

Eastleigh has decided 16 solar farms and approved 100%, taking a median of 2.2 months. See every solar farm decision in Eastleigh

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
1.20.3 km
EfW Incineration · Operational
8.65.7 km
Solar Photovoltaics · Under Construction
1.046.3 km
Solar Photovoltaics · Operational
6.36.8 km
Solar Photovoltaics · Operational
5.87.7 km
Battery · Under Construction
498.3 km
EfW Incineration · Operational
168.7 km
Landfill Gas · Operational
1.58.8 km

How big is Netley Landfill Solar?

Netley Landfill Solar has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Netley Landfill Solar?

REPD records the operator as REG Solarpower/Veolia. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Netley Landfill Solar approved and built?

The application was submitted on 5 August 2014. Permission was granted on 30 October 2014, 3 months later. The site became operational on 31 March 2017, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2044.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode