Netley Landfill Solar is operational in Eastleigh with a recorded capacity of 12 MW, and has been generating since 2017-03-31.

12 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-31
Solar Photovoltaics
Technology
REG Solarpower/Veolia
Eastleigh
Authority
England

Planning and build timeline

Application submitted2014-08-05
Permission granted2014-10-30
3 months after submission
Operational2017-03-31
29 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Eastleigh’s record on solar

Eastleigh has decided 16 solar farms and approved 100%, taking a median of 2.2 months. See every solar farm decision in Eastleigh

Other built sites within 15 km

SiteMWDistance
Netley Landfill Site, Hampshire (Extension)
Landfill Gas · Operational
1.20.3 km
Fawley Waste to Energy Plant
EfW Incineration · Operational
8.65.7 km
Concorde Way, Segensworth - Solar Panels
Solar Photovoltaics · Under Construction
1.046.3 km
Chalcroft Solar Park
Solar Photovoltaics · Operational
6.36.8 km
Raglington Farm
Solar Photovoltaics · Operational
5.87.7 km
Titchfield Lane
Battery · Under Construction
498.3 km
Marchwood ERF
EfW Incineration · Operational
168.7 km
Fairoak Landfill
Landfill Gas · Operational
1.58.8 km

How big is Netley Landfill Solar?

Netley Landfill Solar has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Netley Landfill Solar?

REPD records the operator as REG Solarpower/Veolia. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Netley Landfill Solar approved and built?

The application was submitted on 2014-08-05. Permission was granted on 2014-10-30, 3 months later. The site became operational on 2017-03-31, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2044.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council