Renewable sites › Netley Landfill Site, Hampshire (Extension)
Netley Landfill Site, Hampshire (Extension)
Netley Landfill Site, Hampshire (Extension) is operational in Eastleigh with a recorded capacity of 1.2 MW, and has been generating since 1997-06-18.
Planning and build timeline
| Application submitted | 1995-06-16 |
| Permission granted | 1996-01-26 7 months after submission |
| Operational | 1997-06-18 17 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
- Nutrient-neutrality catchment — Solent: Includes Chichester and Langstone Harbours SPA/Ramsar, Solent and Southampton Water SPA/Ramsar, Solent Maritime SAC, Portsmouth Harbour SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Netley Landfill Solar Solar Photovoltaics · Operational | 12 | 0.3 km |
Fawley Waste to Energy Plant EfW Incineration · Operational | 8.6 | 5.4 km |
Concorde Way, Segensworth - Solar Panels Solar Photovoltaics · Under Construction | 1.04 | 6.6 km |
Chalcroft Solar Park Solar Photovoltaics · Operational | 6.3 | 7 km |
Raglington Farm Solar Photovoltaics · Operational | 5.8 | 8 km |
Marchwood ERF EfW Incineration · Operational | 16 | 8.4 km |
Tavells Lane Solar Farm Solar Photovoltaics · Operational | 5.3 | 8.5 km |
Titchfield Lane Battery · Under Construction | 49 | 8.6 km |
How big is Netley Landfill Site, Hampshire (Extension)?
Netley Landfill Site, Hampshire (Extension) has a recorded installed capacity of 1.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Netley Landfill Site, Hampshire (Extension)?
REPD records the operator as Hampshire Waste Services/ ONYX / Power Plant Services. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Netley Landfill Site, Hampshire (Extension) approved and built?
The application was submitted on 1995-06-16. Permission was granted on 1996-01-26, 7 months later. The site became operational on 1997-06-18, 17 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 800.
Novarly Parcel · official public data, read properly · parcel.novarly.com