Chalcroft Solar Park

Chalcroft Solar Park is an operational 6.3 MW solar farm in Eastleigh, generating since 24 March 2013. Planning permission was granted on 13 December 2012, 2 months after submission. Operator of record: Chalcroft Solar Park.

6.3 MW
Capacity
as recorded in REPD
Operational
Status
since 24 March 2013
Solar Photovoltaics
Technology
Chalcroft Solar Park
Eastleigh
Authority
England

Planning and build timeline

Application submitted28 September 2012
Permission granted13 December 2012
2 months after submission
Operational24 March 2013
3 months after consent

Screening a site of your own?

RedlineUK · £39

Eastleigh approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Chalcroft Solar Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Eastleigh’s record on solar

Eastleigh has decided 16 solar farms and approved 100%, taking a median of 2.2 months. See every solar farm decision in Eastleigh

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
1.52.4 km
Solar Photovoltaics · Operational
5.86.4 km
Solar Photovoltaics · Operational
126.8 km
Landfill Gas · Operational
1.27 km
Solar Photovoltaics · Operational
127 km
Solar Photovoltaics · Operational
37.4 km
Solar Photovoltaics · Operational
6.48.8 km
Solar Photovoltaics · Under Construction
1.049.7 km

How big is Chalcroft Solar Park?

Chalcroft Solar Park has a recorded installed capacity of 6.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Chalcroft Solar Park?

REPD records the operator as Chalcroft Solar Park. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Chalcroft Solar Park approved and built?

The application was submitted on 28 September 2012. Permission was granted on 13 December 2012, 2 months later. The site became operational on 24 March 2013, 3 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1157.