Novarly ParcelRenewable sites

Renewable sitesMynydd Portref

Mynydd Portref

Mynydd Portref is operational in Rhondda Cynon Taf with a recorded capacity of 9.4 MW, and has been generating since 2012-03-26.

9.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-03-26
Wind Onshore
Technology
Gresham House
Rhondda Cynon Taf
Authority
Wales

Planning and build timeline

Application submitted2006-06-26
Permission granted2008-07-01
24 months after submission
Operational2012-03-26
45 months after consent

Rhondda Cynon Taf’s record on onshore wind

Rhondda Cynon Taf has decided 13 onshore wind schemes and approved 92%, taking a median of 23.1 months. See every onshore wind scheme decision in Rhondda Cynon Taf

Other built sites within 15 km

SiteMWDistance
Mynydd Portref Wind Farm extension
Wind Onshore · Operational
120.8 km
Taff Ely Wind Farm
Wind Onshore · Operational
91.5 km
Graig Fatha Farm
Wind Onshore · Operational
2.52.4 km
Coed Ely - Solar Farm
Solar Photovoltaics · Under Construction
63.1 km
Whitehall Farm, Llanharry Road - Solar PV Panels
Solar Photovoltaics · Under Construction
1.33.8 km
Agricultural Land at Trecastle
Solar Photovoltaics · Operational
44.3 km
West of Rhiwfelin Fach Farm
Wind Onshore · Operational
1.54.7 km
Energy Centre Royal Mint
Battery · Operational
204.8 km

How big is Mynydd Portref?

Mynydd Portref has a recorded installed capacity of 9.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Mynydd Portref?

REPD records the operator as Gresham House. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Mynydd Portref approved and built?

The application was submitted on 2006-06-26. Permission was granted on 2008-07-01, 24 months later. The site became operational on 2012-03-26, 45 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3931.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council