Renewable sites › Mynydd Portref
Mynydd Portref
Mynydd Portref is an operational 9.4 MW onshore wind farm in Rhondda Cynon Taf, generating since 26 March 2012. Planning permission was granted on 1 July 2008, 24 months after submission. Operator of record: Gresham House.
Planning and build timeline
| Application submitted | 26 June 2006 |
| Permission granted | 1 July 2008 24 months after submission |
| Operational | 26 March 2012 45 months after consent |
Screening a site of your own?
Rhondda Cynon Taf approves 92% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Mynydd Portref’s recorded coordinate — swap in your own postcode or coordinates.
Rhondda Cynon Taf’s record on onshore wind
Rhondda Cynon Taf has decided 13 onshore wind schemes and approved 92%, taking a median of 23.1 months. See every onshore wind scheme decision in Rhondda Cynon Taf →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 12 | 0.8 km |
Wind Onshore · Operational | 9 | 1.5 km |
Wind Onshore · Operational | 2.5 | 2.4 km |
Solar Photovoltaics · Under Construction | 6 | 3.1 km |
Solar Photovoltaics · Under Construction | 1.3 | 3.8 km |
Solar Photovoltaics · Operational | 4 | 4.3 km |
Wind Onshore · Operational | 1.5 | 4.7 km |
Battery · Operational | 20 | 4.8 km |
How big is Mynydd Portref?
Mynydd Portref has a recorded installed capacity of 9.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Mynydd Portref?
REPD records the operator as Gresham House. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Mynydd Portref approved and built?
The application was submitted on 26 June 2006. Permission was granted on 1 July 2008, 24 months later. The site became operational on 26 March 2012, 45 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3931.