Renewable sites › Graig Fatha Farm
Graig Fatha Farm
Graig Fatha Farm is an operational 2.5 MW onshore wind farm in Rhondda Cynon Taf, generating since 1 December 2021. Planning permission was granted on 15 June 2017, 1 months after submission. Operator of record: Cleanearth.
Planning and build timeline
| Application submitted | 2 May 2017 |
| Permission granted | 15 June 2017 1 months after submission |
| Operational | 1 December 2021 54 months after consent |
Screening a site of your own?
Rhondda Cynon Taf approves 92% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Graig Fatha Farm’s recorded coordinate — swap in your own postcode or coordinates.
Rhondda Cynon Taf’s record on onshore wind
Rhondda Cynon Taf has decided 13 onshore wind schemes and approved 92%, taking a median of 23.1 months. See every onshore wind scheme decision in Rhondda Cynon Taf →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Under Construction | 6 | 1 km |
Wind Onshore · Operational | 12 | 1.7 km |
Wind Onshore · Operational | 1.5 | 2.4 km |
Wind Onshore · Operational | 9.4 | 2.4 km |
Battery · Operational | 20 | 2.4 km |
Wind Onshore · Operational | 9 | 3 km |
Solar Photovoltaics · Under Construction | 1.3 | 3.8 km |
Solar Photovoltaics · Operational | 4 | 3.9 km |
How big is Graig Fatha Farm?
Graig Fatha Farm has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Graig Fatha Farm?
REPD records the operator as Cleanearth. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Graig Fatha Farm approved and built?
The application was submitted on 2 May 2017. Permission was granted on 15 June 2017, 1 months later. The site became operational on 1 December 2021, 54 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6422.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode