Onshore wind planning in Rhondda Cynon Taf

Rhondda Cynon Taf has decided 13 onshore wind schemes and approved 92% of them, taking a median of 23.1 months to decide. Consented capacity: 130 MW. 2 applications still awaiting a decision.

92%
Approved
12 granted · 1 refused
23.1 mo
Median decision
UK 11.5 mo
130 MW
Consented
24 MW refused
3
Appeals
2 allowed on appeal

How Rhondda Cynon Taf compares

Against the 75 UK authorities with 5+ onshore wind decisions, Rhondda Cynon Taf sits in the 91st percentile for approval rate (24 points above the England average) and the 14th percentile for speed.

Decisions by year

35Approved — 1 (2011)111Approved — 1 (2012)112Approved — 1 (2013)113Approved — 1 (2014)114Approved — 1 (2015)115Approved — 1 (2016)116Approved — 2 (2017)217
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (20)

SchemeMWStatusDecided
Llwyncelyn Wind Farm
Cenin Renewables · 18/0877/10
7.2Application Submitted2018-08-01
Llwyncelyn Wind Farm
Cenin Renewables · 15/1635/10 · 23.1 mo to decide
5Revised2017-11-24
Former Nant-y-Gwyddon Landfill Site
Sirius Group · 17/0321/10 · 5.2 mo to decide
1.5Under Construction2017-08-22
Graig Fatha Farm
Cleanearth · 17/0493/10 · 1.4 mo to decide
2.5Operational2017-06-15
Mynydd Pen-y-Graig Wind Farm
Ventient (formerly Infinis) · 15/0831/10
15Application Withdrawn2016-08-17
West of Rhiwfelin Fach Farm
Infinite Renewables · 16/0124/10 · 5.3 mo to decide
1.5Operational2016-07-19
Malthouse Farm
Infinite Renewables · 14/0913/10
1.5Application Withdrawn2015-11-04
Abergorki Wind Farm
Thrive Renewables · 13/0663/10 · 24.8 mo to decide
13.5Awaiting Construction2015-07-23
Maerdy extension
Greencoat UK Wind · 14/0556/10 · 7.7 mo to decide
3Abandoned2014-12-22
Mynydd Portref Wind Farm extension
REG Windpower · 12/0704/10 · 29.7 mo to decide
12Operational2014-12-19
Headwind Taff Ely Wind Farm (Repowering)
RWE Npower Renewables · 11/1468/10 · 16 mo to decide
17.5Planning Permission Expired2013-04-23
Mynydd Bwllfa Wind Farm - Resubmission
Pennant Walters · 09/0393/10 · 36.9 mo to decide
22.5Operational2012-06-01
Fforch Nest Wind Farm pt1
Pennant Walters · P/06/1080/FUL · 56.1 mo to decide
10Operational2011-05-04
Trane Renewable Energy Park
Gamesa Energy · 06/0790
11.9Application Withdrawn2010-06-09
Fforch Nest Wind Farm
Npower Renewables · 06/1688/03 · 36.1 mo to decide
16Abandoned2009-08-25
Mynydd Portref
Gresham House · 06/1325 · 24.2 mo to decide
9.4Operational2008-07-01
Maerdy
Greencoat UK Wind · 11/0198/10 · 17.3 mo to decide
24Operational2008-02-10
Hirwaun Wind Farm
Pennant Walters · 06/1415 · 14.9 mo to decide
24Appeal Refused2007-10-12
Penrhys Wind Farm/Ferndale Power Factory
John Laing Environmental Assets Group · 03/0226 · 24.6 mo to decide
6.4Operational2005-03-01
Taff Ely Wind Farm
Npower Renewables
9Operational

Does Rhondda Cynon Taf approve onshore wind schemes?

Yes — of the 13 onshore wind schemes Rhondda Cynon Taf has decided, 92% were approved (12 granted, 1 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Rhondda Cynon Taf?

The median time from application to decision is 23.1 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Rhondda Cynon Taf consented?

130 MW has been consented across 12 approved schemes, with 24 MW refused. A further 2 applications awaits a decision.

Other technologies in Rhondda Cynon Taf

Solar in Rhondda Cynon TafBattery storage in Rhondda Cynon Taf

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.