Novarly ParcelRenewable sites

Renewable sitesEnergy Centre Royal Mint

Energy Centre Royal Mint

Energy Centre Royal Mint is operational in Rhondda Cynon Taf with a recorded capacity of 20 MW, and has been generating since 2023-08-01.

20 MW
Capacity
as recorded in REPD
Operational
Status
since 2023-08-01
Battery
Technology
Infinite Energy Renewables
Rhondda Cynon Taf
Authority
Wales

Planning and build timeline

Application submitted2019-09-23
Permission granted2020-01-22
4 months after submission
Operational2023-08-01
42 months after consent

Rhondda Cynon Taf’s record on battery storage

Rhondda Cynon Taf has decided 5 battery storage schemes and approved 80%, taking a median of 3.5 months. See every battery storage scheme decision in Rhondda Cynon Taf

Other built sites within 15 km

SiteMWDistance
West of Rhiwfelin Fach Farm
Wind Onshore · Operational
1.50.4 km
Coed Ely - Solar Farm
Solar Photovoltaics · Under Construction
62.4 km
Graig Fatha Farm
Wind Onshore · Operational
2.52.4 km
Mynydd Portref Wind Farm extension
Wind Onshore · Operational
124.1 km
Agricultural Land at Trecastle
Solar Photovoltaics · Operational
44.2 km
Whitehall Farm, Llanharry Road - Solar PV Panels
Solar Photovoltaics · Under Construction
1.34.6 km
Mynydd Portref
Wind Onshore · Operational
9.44.8 km
Berthlwyd Farm
Solar Photovoltaics · Operational
55.1 km

How big is Energy Centre Royal Mint?

Energy Centre Royal Mint has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Energy Centre Royal Mint?

REPD records the operator as Infinite Energy Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Energy Centre Royal Mint approved and built?

The application was submitted on 2019-09-23. Permission was granted on 2020-01-22, 4 months later. The site became operational on 2023-08-01, 42 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7684.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council