Novarly ParcelRenewable sites

Renewable sitesMountsorrel Landfill Site

Mountsorrel Landfill Site

Mountsorrel Landfill Site is an operational 1.6 MW landfill gas site in Charnwood, generating since 1 May 1996. Planning permission was granted on 24 October 1994, 5 months after submission. Operator of record: Redland Aggregates Ltd / Combined Landfill Projects (CLP).

1.6 MW
Capacity
as recorded in REPD
Operational
Status
since 1 May 1996
Landfill Gas
Technology
Redland Aggregates Ltd / Combined Landfill Projects (CLP)
Charnwood
Authority
England

Planning and build timeline

Application submitted7 June 1994
Permission granted24 October 1994
5 months after submission
Operational1 May 1996
18 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Charnwood: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Mountsorrel Landfill Site’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
0.92.1 km
Solar Photovoltaics · Operational
52.9 km
Wind Onshore · Operational
2.54.4 km
Solar Photovoltaics · Under Construction
264.6 km
Solar Photovoltaics · Under Construction
1.76.4 km
Solar Photovoltaics · Under Construction
3.256.8 km
Solar Photovoltaics · Operational
0.28.6 km
Landfill Gas · Operational
2.58.6 km

How big is Mountsorrel Landfill Site?

Mountsorrel Landfill Site has a recorded installed capacity of 1.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Mountsorrel Landfill Site?

REPD records the operator as Redland Aggregates Ltd / Combined Landfill Projects (CLP). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Mountsorrel Landfill Site approved and built?

The application was submitted on 7 June 1994. Permission was granted on 24 October 1994, 5 months later. The site became operational on 1 May 1996, 18 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 749.