Bradgate Quarry Landfill Gas Scheme
Bradgate Quarry Landfill Gas Scheme is an operational 2.5 MW landfill gas site in Hinckley and Bosworth, generating since 1 August 1998. Planning permission was granted on 22 February 1998, 2 months after submission. Operator of record: Waste Recycling Group.
Planning and build timeline
| Application submitted | 15 December 1997 |
| Permission granted | 22 February 1998 2 months after submission |
| Operational | 1 August 1998 5 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Hinckley and Bosworth: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Bradgate Quarry Landfill Gas Scheme’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Under Construction | 0.49 | 3.4 km |
Solar Photovoltaics · Operational | 5 | 3.8 km |
Solar Photovoltaics · Operational | 2.7 | 5 km |
Solar Photovoltaics · Operational | 5 | 5.2 km |
Solar Photovoltaics · Operational | 2.6 | 5.4 km |
Solar Photovoltaics · Operational | 5 | 5.7 km |
Solar Photovoltaics · Under Construction | 3.25 | 5.8 km |
Battery · Operational | 1.5 | 6.5 km |
How big is Bradgate Quarry Landfill Gas Scheme?
Bradgate Quarry Landfill Gas Scheme has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bradgate Quarry Landfill Gas Scheme?
REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bradgate Quarry Landfill Gas Scheme approved and built?
The application was submitted on 15 December 1997. Permission was granted on 22 February 1998, 2 months later. The site became operational on 1 August 1998, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 531.