Renewable sites › Severn Trent STW
Severn Trent STW
Severn Trent STW is an operational 2.5 MW onshore wind farm in Charnwood, generating since 26 February 2014. Planning permission was granted on 16 March 2011, 15 months after submission. Operator of record: Severn Trent Water.
Planning and build timeline
| Application submitted | 21 December 2009 |
| Permission granted | 16 March 2011 15 months after submission |
| Operational | 26 February 2014 35 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Charnwood: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Severn Trent STW’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Under Construction | 26 | 2 km |
Solar Photovoltaics · Under Construction | 0.9 | 2.6 km |
Solar Photovoltaics · Under Construction | 1.7 | 3.5 km |
Solar Photovoltaics · Under Construction | 3.25 | 4.2 km |
Landfill Gas · Operational | 1.6 | 4.4 km |
Solar Photovoltaics · Operational | 5 | 4.6 km |
Solar Photovoltaics · Operational | 0.2 | 5 km |
Solar Photovoltaics · Under Construction | — | 7.5 km |
How big is Severn Trent STW?
Severn Trent STW has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Severn Trent STW?
REPD records the operator as Severn Trent Water. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Severn Trent STW approved and built?
The application was submitted on 21 December 2009. Permission was granted on 16 March 2011, 15 months later. The site became operational on 26 February 2014, 35 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3699.