National Space Centre
National Space Centre is operational in Leicester with a recorded capacity of 0.2 MW, and has been generating since 2019-03-31.
Planning and build timeline
| Application submitted | 2019-01-09 |
| Permission granted | 2019-03-15 2 months after submission |
| Operational | 2019-03-31 1 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Leicester’s record on solar
Leicester has decided 13 solar farms and approved 100%, taking a median of 1.8 months. See every solar farm decision in Leicester →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Hoods Close - Solar Panels Solar Photovoltaics · Under Construction | 1.7 | 2.3 km |
Pepsico International Limited, Leycroft Road - Solar Panels Solar Photovoltaics · Under Construction | 3.25 | 2.4 km |
Newarke St Car Park - Solar Panels Solar Photovoltaics · Under Construction | — | 2.5 km |
Severn Trent STW Wind Onshore · Operational | 2.5 | 5 km |
Kirby Road Solar Panels Solar Photovoltaics · Under Construction | 0.49 | 5.8 km |
Land at and adjacent to Leicester Forest Services Battery · Operational | 1.5 | 6.3 km |
Syston Road - Solar Farm Solar Photovoltaics · Under Construction | 26 | 6.8 km |
Harborough Road Store Solar Photovoltaics · Operational | 0.2 | 7 km |
How big is National Space Centre?
National Space Centre has a recorded installed capacity of 0.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates National Space Centre?
REPD records the operator as EvoEnergy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was National Space Centre approved and built?
The application was submitted on 2019-01-09. Permission was granted on 2019-03-15, 2 months later. The site became operational on 2019-03-31, 1 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7320.