Renewable sites › Morton Wood Farm
Morton Wood Farm
Morton Wood Farm is operational in Wychavon with a recorded capacity of 4.8 MW, and has been generating since 2016-03-15.
Planning and build timeline
| Application submitted | 2014-07-30 |
| Permission granted | 2014-12-15 5 months after submission |
| Operational | 2016-03-15 15 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Wychavon’s record on solar
Wychavon has decided 34 solar farms and approved 97%, taking a median of 4.4 months. See every solar farm decision in Wychavon →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Salford Lodge Solar Photovoltaics · Operational | 5 | 3.2 km |
Bishampton Solar Farm Solar Photovoltaics · Under Construction | 30 | 3.8 km |
Rotherdale Farm - extension Solar Photovoltaics · Operational | 9 | 6.1 km |
Rotherdale Farm Solar Photovoltaics · Operational | 5 | 6.9 km |
Hill and Moor Landfill Scheme Landfill Gas · Operational | 3.4 | 7.4 km |
Bypass Nurseries Solar Farm Solar Photovoltaics · Operational | 3.3 | 9.1 km |
Sytchwythy Fields Solar Photovoltaics · Operational | 1.4 | 9.4 km |
Littleton Solar Farm Solar Photovoltaics · Operational | 30 | 10.3 km |
How big is Morton Wood Farm?
Morton Wood Farm has a recorded installed capacity of 4.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Morton Wood Farm?
REPD records the operator as Sun & Soil. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Morton Wood Farm approved and built?
The application was submitted on 2014-07-30. Permission was granted on 2014-12-15, 5 months later. The site became operational on 2016-03-15, 15 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2041.