Hill and Moor Landfill Scheme
Hill and Moor Landfill Scheme is an operational 3.4 MW landfill gas site in Wychavon, generating since 12 March 1999. Planning permission was granted on 1 October 1996, 5 months after submission. Operator of record: Severn Waste.
Planning and build timeline
| Application submitted | 30 April 1996 |
| Permission granted | 1 October 1996 5 months after submission |
| Operational | 12 March 1999 29 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Wychavon: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Hill and Moor Landfill Scheme’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 9 | 2.3 km |
Solar Photovoltaics · Operational | 5 | 2.4 km |
Solar Photovoltaics · Under Construction | 30 | 3.8 km |
Solar Photovoltaics · Operational | 5 | 7.3 km |
Solar Photovoltaics · Operational | 4.8 | 7.4 km |
Solar Photovoltaics · Operational | 3.3 | 8.3 km |
Wind Onshore · Operational | 1.3 | 8.4 km |
Solar Photovoltaics · Operational | 1.4 | 8.7 km |
How big is Hill and Moor Landfill Scheme?
Hill and Moor Landfill Scheme has a recorded installed capacity of 3.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hill and Moor Landfill Scheme?
REPD records the operator as Severn Waste. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hill and Moor Landfill Scheme approved and built?
The application was submitted on 30 April 1996. Permission was granted on 1 October 1996, 5 months later. The site became operational on 12 March 1999, 29 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 555.