Millennium Extension II
Millennium Extension II is an operational 15 MW onshore wind farm in Scotland, generating since 1 April 2011. Planning permission was granted on 10 August 2009, 7 months after submission. Operator of record: West Coast Energy Ltd/Falck Renewables.
Planning and build timeline
| Application submitted | 6 January 2009 |
| Permission granted | 10 August 2009 7 months after submission |
| Operational | 1 April 2011 20 months after consent |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Millennium Extension II’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 40 | 0 km |
Wind Onshore · Operational | 10 | 0.7 km |
Small Hydro · Operational | 1.6 | 2.9 km |
Large Hydro · Operational | 20 | 2.9 km |
Wind Onshore · Operational | 85 | 8.3 km |
Wind Onshore · Operational | 23.8 | 8.3 km |
Battery · Operational | 49.9 | 9.6 km |
Small Hydro · Operational | 1.3 | 10.8 km |
How big is Millennium Extension II?
Millennium Extension II has a recorded installed capacity of 15 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Millennium Extension II?
REPD records the operator as West Coast Energy Ltd/Falck Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Millennium Extension II approved and built?
The application was submitted on 6 January 2009. Permission was granted on 10 August 2009, 7 months later. The site became operational on 1 April 2011, 20 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2723.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode