Renewable sitesBeinneun Windfarm Extension

Beinneun Windfarm Extension

Beinneun Windfarm Extension is an operational 23.8 MW onshore wind farm in Scotland, generating since 16 February 2017. Planning permission was granted on 2 June 2015, 8 months after submission. Operator of record: Octopus Investments/Blue Energy.

23.8 MW
Capacity
as recorded in REPD
Operational
Status
since 16 February 2017
Wind Onshore
Technology
Octopus Investments/Blue Energy
National
Authority
Scotland

Planning and build timeline

Application submitted14 October 2014
Permission granted2 June 2015
8 months after submission
Operational16 February 2017
21 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Beinneun Windfarm Extension’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
850 km
Small Hydro · Operational
1.34.7 km
Large Hydro · Operational
206.7 km
Small Hydro · Operational
1.67.3 km
Small Hydro · Under Construction
1.17.4 km
Wind Onshore · Operational
107.6 km
Wind Onshore · Operational
158.3 km
Wind Onshore · Operational
408.3 km

How big is Beinneun Windfarm Extension?

Beinneun Windfarm Extension has a recorded installed capacity of 23.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Beinneun Windfarm Extension?

REPD records the operator as Octopus Investments/Blue Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Beinneun Windfarm Extension approved and built?

The application was submitted on 14 October 2014. Permission was granted on 2 June 2015, 8 months later. The site became operational on 16 February 2017, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3619.