Renewable sitesCeannacroc

Ceannacroc

Ceannacroc is an operational 1.6 MW hydro scheme in Highland, generating since 15 January 2017. Planning permission was granted on 18 December 2014, 2 months after submission. Operator of record: Green Highland Renewables.

1.6 MW
Capacity
as recorded in REPD
Operational
Status
since 15 January 2017
Small Hydro
Technology
Green Highland Renewables
Highland
Authority
Scotland

Planning and build timeline

Application submitted18 October 2014
Permission granted18 December 2014
2 months after submission
Operational15 January 2017
25 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Highland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Ceannacroc’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Large Hydro · Operational
200.6 km
Wind Onshore · Operational
102.6 km
Wind Onshore · Operational
152.9 km
Wind Onshore · Operational
402.9 km
Wind Onshore · Operational
857.3 km
Wind Onshore · Operational
23.87.3 km
Small Hydro · Operational
1.310.9 km
Small Hydro · Operational
1.512.1 km

How big is Ceannacroc?

Ceannacroc has a recorded installed capacity of 1.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ceannacroc?

REPD records the operator as Green Highland Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ceannacroc approved and built?

The application was submitted on 18 October 2014. Permission was granted on 18 December 2014, 2 months later. The site became operational on 15 January 2017, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4707.

Novarly Parcel · official public data, read properly · parcel.novarly.com