Millennium Windfarm
Millennium Windfarm is an operational 40 MW onshore wind farm in Highland, generating since 15 July 2008. Planning permission was granted on 1 April 2005, 16 months after submission. Operator of record: Renewable Development Company (RDC) Scotland (Ltd) for FALCK RENEWABLES.
Planning and build timeline
| Application submitted | 1 December 2003 |
| Permission granted | 1 April 2005 16 months after submission |
| Operational | 15 July 2008 39 months after consent |
Screening a site of your own?
Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Millennium Windfarm’s recorded coordinate — swap in your own postcode or coordinates.
Highland’s record on onshore wind
Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 15 | 0 km |
Wind Onshore · Operational | 10 | 0.7 km |
Small Hydro · Operational | 1.6 | 2.9 km |
Large Hydro · Operational | 20 | 2.9 km |
Wind Onshore · Operational | 85 | 8.3 km |
Wind Onshore · Operational | 23.8 | 8.3 km |
Battery · Operational | 49.9 | 9.6 km |
Small Hydro · Operational | 1.3 | 10.8 km |
How big is Millennium Windfarm?
Millennium Windfarm has a recorded installed capacity of 40 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Millennium Windfarm?
REPD records the operator as Renewable Development Company (RDC) Scotland (Ltd) for FALCK RENEWABLES. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Millennium Windfarm approved and built?
The application was submitted on 1 December 2003. Permission was granted on 1 April 2005, 16 months later. The site became operational on 15 July 2008, 39 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4682.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode