Novarly ParcelRenewable sites

Renewable sitesMillennium Extension

Millennium Extension

Millennium Extension is an operational 10 MW onshore wind farm in Highland, generating since 1 December 2008. Planning permission was granted on 12 January 2008, 10 months after submission. Operator of record: West Coast Energy /Falck Renewables.

10 MW
Capacity
as recorded in REPD
Operational
Status
since 1 December 2008
Wind Onshore
Technology
West Coast Energy /Falck Renewables
Highland
Authority
Scotland

Planning and build timeline

Application submitted10 March 2007
Permission granted12 January 2008
10 months after submission
Operational1 December 2008
11 months after consent

Screening a site of your own?

RedlineUK · £39

Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Millennium Extension’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Highland’s record on onshore wind

Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
150.7 km
Wind Onshore · Operational
400.7 km
Large Hydro · Operational
202.5 km
Small Hydro · Operational
1.62.6 km
Wind Onshore · Operational
857.6 km
Wind Onshore · Operational
23.87.6 km
Battery · Operational
49.99.9 km
Small Hydro · Operational
1.310.2 km

How big is Millennium Extension?

Millennium Extension has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Millennium Extension?

REPD records the operator as West Coast Energy /Falck Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Millennium Extension approved and built?

The application was submitted on 10 March 2007. Permission was granted on 12 January 2008, 10 months later. The site became operational on 1 December 2008, 11 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3598.