Renewable sites › Marsh Farm Hilperton
Marsh Farm Hilperton
Marsh Farm Hilperton is operational in Wiltshire with a recorded capacity of 9.1 MW, and has been generating since 2015-03-14.
Planning and build timeline
| Application submitted | 2014-01-29 |
| Permission granted | 2014-04-30 3 months after submission |
| Operational | 2015-03-14 10 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Wiltshire’s record on solar
Wiltshire has decided 103 solar farms and approved 93%, taking a median of 4 months. See every solar farm decision in Wiltshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Trowbridge Sewage Treatment Works Sewage Sludge Digestion · Operational | 1.2 | 2.8 km |
Cockhill Solar Farm Solar Photovoltaics · Operational | 20 | 2.9 km |
Land north of Ashton Road Solar Photovoltaics · Operational | 4 | 3.1 km |
Trowle Common Solar Photovoltaics · Operational | 5 | 3.7 km |
Kingston Farm Solar Photovoltaics · Operational | 5 | 4.1 km |
Roundponds Farm Solar Park Solar Photovoltaics · Operational | 13.5 | 4.5 km |
Norrington Common Solar Farm Solar Photovoltaics · Operational | 10 | 4.7 km |
Land West Side of Axe and Cleaver Lane Solar Photovoltaics · Operational | 5 | 5.9 km |
How big is Marsh Farm Hilperton?
Marsh Farm Hilperton has a recorded installed capacity of 9.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Marsh Farm Hilperton?
REPD records the operator as Foresight. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Marsh Farm Hilperton approved and built?
The application was submitted on 2014-01-29. Permission was granted on 2014-04-30, 3 months later. The site became operational on 2015-03-14, 10 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2373.
Novarly Parcel · official public data, read properly · parcel.novarly.com