Novarly ParcelRenewable sites

Renewable sitesTrowbridge Sewage Treatment Works

Trowbridge Sewage Treatment Works

Trowbridge Sewage Treatment Works is operational in Wiltshire with a recorded capacity of 1.2 MW, and has been generating since 2016-04-19.

1.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-04-19
Sewage Sludge Digestion
Technology
Wessex Water
Wiltshire
Authority
England

Planning and build timeline

Application submitted2012-09-28
Permission granted2013-02-27
5 months after submission
Operational2016-04-19
38 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Cockhill Solar Farm
Solar Photovoltaics · Operational
200.6 km
Trowle Common
Solar Photovoltaics · Operational
51 km
Kingston Farm
Solar Photovoltaics · Operational
52.8 km
Marsh Farm Hilperton
Solar Photovoltaics · Operational
9.12.8 km
Land West Side of Axe and Cleaver Lane
Solar Photovoltaics · Operational
54 km
Land at Poles Hole Farm
Solar Photovoltaics · Operational
6.84.3 km
Land north of Ashton Road
Solar Photovoltaics · Operational
44.5 km
Brook Hall Farm
Solar Photovoltaics · Operational
4.75.3 km

How big is Trowbridge Sewage Treatment Works?

Trowbridge Sewage Treatment Works has a recorded installed capacity of 1.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Trowbridge Sewage Treatment Works?

REPD records the operator as Wessex Water. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Trowbridge Sewage Treatment Works approved and built?

The application was submitted on 2012-09-28. Permission was granted on 2013-02-27, 5 months later. The site became operational on 2016-04-19, 38 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6093.